Since the last article, in the Winter 08 edition
of Pipeline, we have finally progressed from the birth of the barge to
the berth of the barge as after more than 8 months in build we were
launched (in the dark – photos awful) at Red Hill Marina on Tuesday 9th
December and after an extended delay due to the river being in flood we
started the journey to our permanent mooring at Barrow-upon-Soar – more
of which later.
On the day of the launch we set off to Red Hill Marina (the site of the
2009 IWA National Festival) to see the arrival of the boat and the
set-up for the lift from the road trailer into the River Soar when we
crossed fingers, legs, eyes and anything else as it was stressful seeing
the boat (our main future home whilst we rent out the bricks and mortar)
hoisted into the air supported by wire rope slings. Fortunately all went
well and eventually the boat was gradually and carefully lowered into
the water to be quickly examined for any leakage by Piper Boats before
the slings were finally removed and the boat floated free. The weight of
the boat was recorded by the crane as 40.5 tonnes. New PBOC member Paul
Wixey’s sailaway Piper narrowboat was also launched on the same
afternoon and on the Friday (before the flooding began) he departed Red
Hill for Willington where I believe he plans to complete the fit-out.
Following the launch there were two days of commissioning by Piper Boats
during which the electrical, mechanical and hydraulic systems received
attention and the main engine was started – very quiet and smooth. The
electrical systems, including the Mastervolt 6kW generator, were given a
thorough testing to ensure that they were fully integrated and that any
automatic changeovers from inverter to generator to shore supply worked
and that our existing 2kW Honda emergency generator was also compatible.
I was then given instructions on the operation of the various systems
that I had already asked questions about during the many Saturday visits
to Biddulph. I thought on the basis that to try and absorb all the
technical and operating information in one short hit was impossible and
that an extended ‘drip feed’ of the information was preferable – I still
managed to forget some procedures though, but that is what the
instruction manuals are then for. Following the commissioning, our
carpet fitter came along over a two day period to fit the carpets and
this was followed by the upholsterers who delivered the sofa bed and
other soft furnishings. The result of fitting the underlay and carpet is
that the floor was no longer a heat sink and sounds no longer
reverberate as much. The Refleks oil stove was left burning for nearly a
week on a low heat to keep the inside temperature at a reasonable level
during the very wet and cold period following the launch. December is
definitely not the best month for a boat launch.
We had originally decided to take three days (river flow and weather
dependant – wheelhouse down – cabriolet mode) over the journey back from
Red Hill to Barrow upon Soar where we have our permanent mooring.
The first of these days would be spent on the wide Trent where I could
become familiar (ie have a play) with the size and handling of the boat
before re-entering the narrower Soar Navigation locks. On Sunday 21st
December two friends and I took the boat out onto the still swollen and
fast running Trent for its first outing as far upstream as Sawley Locks
and back and I was pleased to note that despite the strong stream
conditions on the Trent the boat just ploughed through the water without
any hesitation. The turn at Sawley Lock was somewhat dramatic as it was
a battle between the forces of nature (the combined flow of the rivers
Trent & Derwent) and the forces of a Beta engine and I am pleased to say
that the forces of Beta won which prevented us being swept sideways into
the bridge buttresses whilst turning through 180° in the strong stream
conditions. I have made this same turn many times in our narrowboat
under calmer conditions but this was the first and last time that I
would consider doing it in the conditions which prevailed that day. On
our brief return to Red Hill we demounted and stowed the upper
wheelhouse sections and set off on our journey towards Barrow. The day
was cold (but dry) with a stiff breeze blowing which made for
uncomfortable travelling conditions in the now open wheelhouse – very
familiar to narrowboat steerers. This was the first time that I had
handled the boat through the locks on the Soar and was pleased to be
told that I had around 10” (250mm) clearance on both sides of the boat –
not that I could tell from the steering position as you cannot see down
the side of the hull as a reference. Our journey ended abruptly 5 locks
later at Zouch where the river Soar flood gates were still closed and so
we had to reverse back, moor up and rebuild the wheelhouse outside of
the canal side Rose & Crown pub which benefited greatly over the
following days from our enforced stoppage however, the food was really
good. It was to be Boxing Day before we could move the boat again as we
had to wait for the level of the Soar to fall and our friends had other
commitments during the run up to Christmas but on Boxing Day the weather
was sunny, dry, cold and thankfully calm when we eventually set off
mid-morning for the journey to Barrow via Loughborough. Although the
journey itself was without significant incident there were some testing
moments whilst negotiating the arched canal bridges between Loughborough
and Barrow. On two bridges in particular the arch was so low that there
was only around 2” (50mm) clearance on the offside between the arch
masonry and the handrails around the back of the boat but there was
plenty of evidence on the arch and headwalls where some boaters had not
been so fortunate. A number of tight turns on the route such as the
‘Devils Elbow’ turn under the A6006 at Zouch, the right angled turn
under Chain Bridge in Loughborough and the restricted approach to Barrow
Deep Lock made for some interesting moments but by a good team effort
from the lookouts at the bow we did not provide much entertainment for
the spectators. We finally arrived at Meadow Farm Marina at Barrow mid
afternoon, quickly rebuilt the wheelhouse and after a hot drink and
grateful thanks ferried our friends back to their cars that had been
left that morning at the Rose & Crown.
One steering characteristic that I have had to become used to is the
time delay between moving the steering wheel and the boat responding;
unlike a narrowboat where the response to the tiller is almost
instantaneous. The problem here is that you initially try to compensate
for this delay by moving the wheel more and end up over-steering
producing a meandering path that doesn’t look very good but very quickly
you learn to anticipate the moves and then allow the necessary time
beforehand. I also have to admit that without the bow thruster I would
have been up the proverbial creek sans paddle; the hope and intention is
that with handling experience our reliance on the bow thruster will
become very much less but in the meantime I’m extremely glad that it
works. Yes I did scuff a small amount of Comastic from the hull due to
inexperience whilst entering the locks but these scuffs were slight and
are easily retouched. Kath & I hope to attend a barge handling course
later this year to provide us with more confidence and to learn the
‘correct’ way of working the boat.
Over the remaining Christmas/New Year period we stayed on the boat where
we became more familiar with the various systems, the unique boat
‘sounds’ and also to allow me to fit rails, curtains etc and to continue
with the wall tiling in the shower room - although a relatively compact
room this task seemed never ending but the end result is well worth
while. The extended holiday period was a really enjoyable break and, as
our live-in grandson was away for a few days, we were able to
concentrate on the various finishing off jobs. Unfortunately the adverse
weather in January and February precluded any attempts to take the boat
out for a jolly along the Soar as the river was almost constantly in
flood but this served to encourage us to complete as many jobs as
possible.
For us this now marks the end of the beginning that has involved many
hours of drawing, debating layouts and frustrations but in general a
great deal of pleasure designing what is to become our future home (we
plan to move onboard around Easter time) and I hope to contribute one or
two future updates on our experiences. We intend to take the boat down
to Loughborough for the May Day bank holiday boat festival by which time
it should be ‘complete’ (whatever that means in boat terms) and we are
hoping for some good weather as all profits from the festival benefit
the local charities.
Some of the longer standing PBOC members may recall an article that I
wrote in Pipeline in 2003 titled ‘Owning a Piper Boat – The Positives &
Negatives’ (still on the PBOC website) where I posed the question at the
end of the article ‘would I buy another Piper boat?’ I said an emphatic
YES at that time and nothing that we have experienced during this latest
build has changed my feelings.
Kath, and I are indebted particularly to Simon, Andy, Dave, Duncan, Dan
and Matt as well as Lee, Stuart and Howard (plus others at Piper Boats)
for producing a good looking, sturdy and well finished boat that has
already received many very favourable comments from passers-by as well
as other boaters.
By Peter Fairhurst
Return
to Pipeline Index
Back
to Part 3
Continue
to 1st Impressions & Use
|